Farmingdale board reviews water‑treatment progress and funding commitments
Summary
Board updates show Well 1–3 AOP/GAC systems now operational, a $1 million county grant (half received), a requested $1.1 million federal allocation, and new testing costs of about $16,000 per well as the village advances a May 1, 2025 completion target for all wells.
Get email alerts on the Water Treatment topic
No spam. Unsubscribe anytime.
The Board of Trustees received an update on the village’s water‑treatment program, reporting that sampling and testing for Advanced Oxidation Process/Granular Activated Carbon (AOP/GAC) at Wells 1–3 is ongoing and the wells are now operational. Officials said a new steel building covering GAC tanks is complete and Plant 2 construction is underway as part of the treatment upgrades.
The meeting noted tighter testing requirements and added costs: additional testing for newly monitored contaminants was estimated at approximately $16,000 per well. Village documents and staff reports set a master schedule managed by PRI that aims to complete work on all wells by 2025‑05‑01. The board also reported financial progress: County Legislator John Ferretti committed a $1,000,000 grant to offset project costs, with $500,000 received to date, and Congressman Thomas Suozzi has been informed of a requested $1.1 million allocation in the 2025–2026 federal budget (described in the minutes as a request, not an approved reimbursement). Deputy Clerk Daniel Ruckdeschel assisted in finalizing funding submissions.
Board members asked staff to continue following up on legal‑settlement funds and potential federal and county sources. D&B will evaluate the ground tank roof and structure and provide analysis related to antennae replacement on the elevated tank; village staff said those studies are part of preparing the projects for final funding and construction phases.
Next steps noted in the work session include continued testing, D&B evaluations, and ongoing grant follow‑up to secure the remaining funds needed to complete the treatment work by the May target.