Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Contracts topic

No spam. Unsubscribe anytime.

Council approves pay application No. 14 to APX Construction; retainage of about $5,000 remains

Dell Rapids City Council · December 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved pay application No. 14 for APX Construction after staff said a prior $2,873.34 change order was converted into the application; approximately $5,000 remains with APX as retainage to cover spring repairs to disturbed landscaping.

The Dell Rapids City Council approved pay application No. 14 to APX Construction at its Dec. 15 meeting.

Staff reported that a previously approved change order (change order 3 for $2,873.34) was converted into pay application No. 14 and that roughly $5,000 remains with APX as retainage. “In the last Council meeting, we approved change order 3 for $2,873.34 has been just converted into a pay application. There's still $5,000 left with APX and retainage,” the city administrator said.

Council members asked about staining and sealing of park timbers and pillars; staff said some materials may need a different treatment and offered to consult the public works director. The council moved and approved pay application No. 14 by voice vote.