Barton Malow reports Bid Pack #2 under budget; CTE designs complete and bids forthcoming
Summary
Evan Chechak of Barton Malow updated the Board that Bid Pack #1 is on schedule, Bid Pack #2 came in under budget, and Bid Pack #3 (CTE additions) design work is complete with bids to be issued next week.
Get email alerts on the Capital Planning topic
No spam. Unsubscribe anytime.
Evan Chechak of Barton Malow briefed the Board on the district's capital improvement program. He reported that Bid Pack #1 is tracking on schedule, Bid Pack #2 came in under budget, and Bid Pack #3—which includes CTE additions—has completed designs and will go out to bid the following week.
The update situates the Board's later contract approvals (including the Bid Pack #2 electrical award) within the district's phased construction plan. The minutes record the update as informational; no formal Board action on Bid Pack #3 or Bid Pack #4 was taken at this meeting.