Council supports application for $1M revenue‑sharing to close funding gap on I‑81 Exit 243 project

Harrisonburg City Council · August 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works presented a plan to apply for $1 million in VDOT revenue‑sharing (50/50) to close a $2 million shortfall for the Exit 243 improvements; council authorized a resolution of support and staff will seek a $1 million allocation in the FY27 budget if the application succeeds.

Tom Hartman returned to the podium to present a revenue‑sharing resolution for the I‑81 Exit 243 improvement project. He said the project's original SmartScale estimate exceeded current costs and the city faces roughly a $3.8 million deficit; VDOT identified an extra $1.8 million in SmartScale funds and the city proposes applying for $1 million in revenue sharing (matched by $1 million from the city) to close the remaining gap.

Hartman said the improvements would add a second left‑turn lane in the southbound direction and a receiving lane on the on‑ramp to better align traffic movements, and would also add turning capacity on the exit to reduce conflicts in a truck‑heavy commercial corridor. If supported, the application would be submitted in mid‑September and the city would seek the matching $1 million in the FY27 budget; right‑of‑way and construction phases are planned with construction scheduled to begin in 2028 if funding and approvals align.

Council voted to adopt the resolution of support by roll call; staff will submit the application and incorporate the match request into next budget cycle as appropriate.