Committee advances plan for new low-side water tower at Brickyard Park site
Summary
Staff recommended a new low-side water tower to boost storage and pressures in lower-elevation neighborhoods; the committee moved the ordinance to the Council agenda so the city can pursue loan funding and finalize design.
Get email alerts on the Water Storage topic
No spam. Unsubscribe anytime.
City Engineer Glenn Davis told the committee the water system’s low-pressure zone lacks sufficient storage and that a new low-side tower would improve pressure and flow in lower-elevation neighborhoods. A preliminary site study identified Brickyard Park as a preferred location and the project is currently in design.
The committee unanimously voted to forward the ordinance to the full Council so staff can pursue Water Supply Revolving Loan Account nomination and line up construction to start in the fall, preventing future capacity struggles in the area, Davis said.