Board approves paving plan using HUD sidewalk funds; North Young reconstruction estimated at $66,000
Summary
City staff advised that HUD sidewalk grant funds can be used to pave streets adjacent to the sidewalk project; North Young needs full reconstruction (~$66,000) while North Morgan would cost about $65,000 for a topcoat. Board authorized paving and contracting Nitzschke for demolition.
Get email alerts on the Paving topic
No spam. Unsubscribe anytime.
City Administrator Kim Rogers told the board the HUD sidewalk grant can fund paving of streets that the sidewalk project touches. She specifically identified North Morgan and North Young as candidates and recommended full reconstruction for North Young rather than a mere topcoat, warning a topping would not last given the road—ondition. Rogers estimated reconstruction of North Young at about $66,000 and a topcoat on North Morgan at about $65,000, and said city employees could save roughly $10,000 by performing demolition themselves if feasible.
After discussion about durability and contractor responsibilities, Vice Mayor Jonathan Newberry moved to pave the streets as discussed and have contractor Nitzschke perform the demolition; Commissioner Margaret Maze seconded and the motion passed.