Board reviews Motorola radio project; committee recommends Change Order #4 reducing contract by $15,100
Summary
Public Safety staff reported ongoing work and remaining grounding/wiring issues on the Motorola radio project; the Public Safety Committee recommended approval of Change Order #4, which County Administrator Shawn Utt said will reduce the contract price by $15,100. Payment on incomplete grounding work will be withheld until finished.
Get email alerts on the Motorola Radio Project topic
No spam. Unsubscribe anytime.
Public Safety staff updated the Board on the Motorola radio system project, reporting incomplete grounding and remaining code plug issues and noting a new Motorola project manager, Paul Bromley, has taken a more hands-on role. Director of Public Safety Curtis Crawford said invoices for grounding work have been received but the work remains incomplete and that payment would be withheld until the work is finished.
County Administrator Shawn Utt reviewed Motorola Radio Project Change Order #4 and said it is a beneficial adjustment that reduces the contract price by $15,100. The Public Safety Committee recommended approval and the recommendation passed unanimously as a committee action; the Board recorded the committee’s recommendation in the meeting record.