Bloomington board approves $249,920 pay application for Wall Street paving

Village of Bloomington Board · June 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Village of Bloomington approved Pay Application #8 to JI Construction for $249,920 to complete Wall Street paving; Delta 3 Engineering reported the street is about 75% complete and the project cost overrun estimate fell to roughly $55,000 above contract despite added work.

The Village of Bloomington board unanimously approved Pay Application #8 to JI Construction for $249,920 to continue paving work on Wall Street. Delta 3 Engineering notified the board that Wall Street is about 75% complete, with clean-up and landscaping expected by June 6.

Mark Digman of Delta 3 Engineering told trustees that his earlier estimate of roughly $70,000 over contract had fallen to about $55,000 despite numerous added items including site fill (~$66,000), storm sewer on Spruce Road (~$15,000), paving on West Court Street (~$40,000), additional water services and laterals (~$15,000), and tree removals (~$4,000). The motion to approve the $249,920 pay application was made by Trustee Dennis Moris and seconded by Trustee Alan Mergen and carried unanimously.