Village to televise sewers and seek bids ahead of 2031 Highway 35 utility decision
Summary
DOT has asked whether the village wants utilities replaced with a 2031 Highway 35 resurfacing. Delta 3 recommended televising sanitary sewers and basement inspections; Director Leitzinger found lead water services and was directed to request bids before January.
Get email alerts on the Infrastructure Planning topic
No spam. Unsubscribe anytime.
The board reviewed Wisconsin DOT correspondence about a planned 2031 resurfacing of Highway 35 and a March 1, 2026 deadline to decide whether to replace village-owned utilities as part of that project. Mark Digman of Delta 3 Engineering recommended televising the sanitary sewer system to assess condition and conducting basement inspections to identify possible lead water service lines before committing to utility work.
Director of Public Works Keith Leitzinger told trustees he has discovered lead water service lines during recent inspections, which raises EPA-related replacement concerns. The board directed Leitzinger to contact Mark Digman to arrange sewer televising and to request bids for that work before the January meeting so the village can make an informed decision about utility replacement in coordination with the DOT timeline.