Board approves Early Learning Center bid package amid project planning
Summary
The Board approved the Early Learning Center bid package 6–1 after Operations Director Rob Gleeson reviewed scope, cost estimates and the contractor evaluation process; the project will move forward to solicitation and evaluation.
Get email alerts on the Early Learning Center topic
No spam. Unsubscribe anytime.
Operations & Transportation Director Rob Gleeson presented the Early Learning Center bid package at the April 27 workshop, outlining scope, project components, cost estimates and an anticipated timeline. He said the package aligns with district facility needs and long‑term planning and described the process the district will use to solicit and evaluate contractor proposals.
Vice President Parker‑Sternburgh moved to approve the bid package and Treasurer Nelson supported the motion; the Board approved the motion 6–1. The approval allows staff to proceed with the procurement steps laid out in the bid documents and prepare for contractor selection and project scheduling.