Supervisor Hock updates council on Chain Park completion, pickleball courts and 1st Street repairs

South Bend City Council · August 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Supervisor Hock said outstanding Chain Park completion items remain (corner collars, fence height adjustments), reported new pickleball nets installed, and described minor defects found during a 1st Street reconstruction walkthrough; striping was scheduled for the 22nd.

Supervisor Hock gave the council a multi-part project update, beginning with Chain Park. He said the project is near completion but still has physical-completion items to finish — specifically corner collars for posts and fence-height adjustments — and that he inspected the site recently. "We added some pickleball nets down there inside of a a steel locker," Hock said, noting community interest in the courts.

On the 1st Street reconstruction project, Hock said he walked the site with contractors and engineers and identified a few minor issues — small cracks in gutters and some surface waviness in the asphalt — and that the team will do another walkthrough to determine corrective measures. He also said striping for the project is scheduled "on the 22nd."