Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
Township approves $360,000 asphalt and $140,000 chip-seal engineering projects for 2025
Summary
Silver Creek Township supervisors voted unanimously to approve proposed 2025 road engineering projects allocating $360,000 for asphalt work and $140,000 for chip seal. Maintenance staff will pursue engineering and move the projects forward.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
Silver Creek Township supervisors voted Nov. 7 to approve proposed 2025 road engineering projects that allocate $360,000 for asphalt work and $140,000 for chip seal.
Supervisor Ryan Nelson moved to approve the dollar amounts; Vice Chairman Brandon Geyen seconded and the motion carried 5-0. Maintenance staff will contact the township engineer to advance the selected projects and schedule work in 2025. The board’s action authorizes staff to proceed with engineering for the identified amounts rather than committing final construction contracts.