Trustees review Oak, Railroad and Washington street work in Nehawka plan
Summary
The board considered an overlay for Oak Street, paving about 230 feet of Railroad Avenue with a new sewer main, and grinding/overlay of Washington Avenue between Main and Sherman; consultant will include these projects in the 1 & 6‑Year update.
Get email alerts on the Street Projects topic
No spam. Unsubscribe anytime.
During the July 21 special meeting, trustees and consultant discussed several additional street projects to be captured in the 1 & 6‑Year Street Plan update. Items listed in the minutes include an overlay of Oak Street, paving roughly 230 feet of Railroad Avenue accompanied by the installation of a new sewer main, and grinding and overlay of Washington Avenue between Main Street and Sherman Avenue.
The minutes do not include cost estimates for these specific projects nor record any motions or votes approving them; the consultant, Scott Hrabik, will update the formal plan for future board review and potential funding actions such as a MAPA grant application.