Hudson Oaks official outlines joint wastewater route, timeline and costs for Willow Park project

Municipal Utility Board · February 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A Hudson Oaks official presented a routing and timeline for a jointly owned Willow Park wastewater facility and transfer station, estimating about $10 million in near-term pipeline and lift-station work and projecting key design and construction milestones through mid-2026.

Sterling Narin, introduced to the board as a representative from the city of Hudson Oaks, described the routing for a transfer station and lift station that will send flow under I-20 to a jointly owned Willow Park treatment facility. He said the team has finalized routing, resolved easements with affected property owners and anticipates final design submittal by April with advertisement and contract award in May–June and construction starting in July 2025.

"Lift station about 1.8. Forest Main about 7.8. Total cost of these 2 projects, just under $10,000,000," Narin said, summarizing staff estimates. He also told the board Willow Park expects its treatment plant to be operational in October 2025, and Weatherford staff discussed renewal timing for Weatherford’s existing wholesale contract (current contract period runs through June 30, 2026) to ensure continuity if the construction schedule shifts. The presentation noted outstanding TxDOT permits (a driveway permit and a crossing) and work with county precinct staff to coordinate Bankhead/FM crossings and avoid duplicate construction.