Commissioners authorize grant commitment, bridge inspection contract and several right-of-way permits
Summary
The board agreed to sign a Community Crossing grant commitment for 500 E (total cost $893,085; county share $178,617), approved a $247,170.14 SJCA bridge inspection contract to be paid over four years, and cleared right-of-way work by private and utility companies.
Get email alerts on the Roads And Bridges topic
No spam. Unsubscribe anytime.
Blackford County commissioners on Oct. 6 approved multiple public-works items, including a Community Crossing grant commitment for work on 500 E and a countywide bridge inspection contract with SJCA.
Highway Superintendent John Pluimer asked the board to sign a commitment letter for a Community Crossing grant for 500 E. Pluimer told commissioners the total project cost is $893,085 and the county’s 20% share would be $178,617; he said the county would apply for the grant by the end of the month. “Total project cost is $893,085; county would pay 20% for a cost of $178,617,” Pluimer said. The board voted to sign the commitment letter (motion by Dan Borgenheimer; second by Laura Coons; vote 3–0).
Pluimer also presented a countywide bridge inspection contract with SJCA totaling $247,170.14, which the county will pay over four years; the commissioners accepted the contract on a motion by Coons and second by Borgenheimer (vote 3–0). The board approved right-of-way work requests for BSM Groups to install fiber on Angling Pike and for AEP to replace poles in Montpelier (450 N and Warren Ave); it also approved the City of Hartford’s temporary use of county dumpsters and a rollback truck for house demolition, with the city’s insurance covering the use.
The transcript records approvals but does not include detailed project schedules, grant application documents, or copies of the SJCA contract beyond the total amount and payment plan.