County reports progress on Station 9 renovation and burn-building training site
Summary
Staff said Station 9 in Mountville has been demoed and will be re-skinned this week, with interior build-out to follow; the burn-building training site is being prepared with Connex trailers and site work expected to finish by early September.
Get email alerts on the Fire Station Maintenance topic
No spam. Unsubscribe anytime.
Jay Anderson and fire staff updated the board on construction and training-facility work. Anderson said the Station 9 renovation in Mountville began last week, with interior demo complete and metal skin removed; crews expected to pressure-wash, prime and re-skin the building this week and move to interior build-out soon.
Fire staff also reported progress on the burn-building training site: Connex trailers have been delivered and site clearing and grading work is nearly finished, with staff projecting the training area will be ready by the first weeks of September.