Council approves change order after deeper-than-expected soils at FlowEQ Basin

Anamosa City Council · March 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A change order for the FlowEQ Basin (WRH Inc.) was approved after engineers reported geotechnical borings were off by roughly two feet, requiring additional excavation and structural backfill; the consultant said the not-to-exceed amount may be reduced as more data arrive.

Council considered Change Order No. 1 for WRH Incorporated tied to the FlowEQ Basin project after staff and the project geotechnical consultant reported unanticipated subsurface conditions. Nick of Steiner Associates explained the contractor found bedrock about two feet deeper than design borings had indicated, and that additional borings over the prior two weeks showed variable soil conditions concentrated in the north part of the tank footprint.

Nick said the change order is a not-to-exceed allowance for additional excavation and replacement with structural backfill, and that the team expects the number could decrease once final depths are confirmed. Council members asked how the borings could have missed bedrock; Nick said the original three borings were consistent on paper but onsite conditions differed and that he is working with the geotechnical engineer and contractor to produce a detailed explanation and updated cost information. Council approved the change order to avoid later, costlier failures.