County engineer schedules Sept. bridge replacements, reports road regrades and culvert work

Van Buren County Board of Supervisors · August 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County Engineer Ryne Thornburg reported bridge pile replacement work planned the week of Sept. 22, 2025, on Hickory Avenue north of Hwy 16 and Hawk Drive north of Farmington, and ongoing regrades on Eagle Drive and Timber Ave; Grout Scouts will line culverts under Route W46 this week.

County Engineer Ryne Thornburg told the Van Buren County Board on Aug. 11 that quotes have been received and work is scheduled the week of Sept. 22, 2025, to replace piles at two bridge abutments: the bridge on Hickory Avenue north of Highway 16 and the bridge on Hawk Drive north of Farmington.

Thornburg also reported ongoing regrade work on Eagle Drive to Davis County, Timber Ave south of Bonaparte (including ditching work), and Eagle Drive between Bonaparte and Farmington. Meeting notes recorded that Grout Scouts will complete culvert lining under Route W46 during the week and will address additional culverts that need repair before leaving the county. Thornburg further noted that private haulers have been removing loads of lime from the County Quarry and that staff are monitoring that activity.