Tonkawa approves $20,651.63 purchase for 44th Street lift station pump; installation planned Oct. 22
Summary
The Tonkawa Municipal Authority approved purchase of a Barnes Vertical Dry Pit 15 hp, 460‑volt pump for the 44th Street lift station at a cost of $20,651.63 from Edward's Equipment. Water Superintendent Clint Ross said, if approved, he planned to install the pump on Oct. 22 and return operations to normal without 24/7 monitoring.
Get email alerts on the Utility Operations topic
No spam. Unsubscribe anytime.
Clint Ross, Water Superintendent, briefed the board on the status of the 44th Street lift station and reported the facility needs a new pump. Ross said, "If approved, he plans to install the new pump on Wednesday morning, October 22, 2025, and be back to normal operations with no need for 24/7 monitoring." The board considered a purchase quote from Edward's Equipment for a Barnes Vertical Dry Pit 15 hp 460‑volt pump at $20,651.63.
Trustee Charles Conaghan moved to approve the Edwards Equipment quote and Trustee Kenneth Smith seconded; the motion passed with recorded ayes from Trustees Harris, Conaghan, Burns and Smith and Trustee Simpson absent. Ross indicated the existing pump would be retained as a backup at the Rogers Lift Station.