Council approves $650,159 bid for Cook Park improvements; grant covers half

Galesburg City Council · April 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Lockwood Excavating won the $650,159 low bid for Cook Park improvements; staff said the work is expected to begin in June 2025, be roughly 50% funded by a grant (referred to in the transcript as 'onslaught/Ozlad'), and that later phases could bring total costs to about $1.125 million.

The council unanimously approved a $650,159 contract with Lockwood Excavating & Construction for the first phase of Cook Park improvements.

City staff described the bid as the low and best of six proposals and said the project will include a playground, picnic shelter and restrooms, benches, sidewalks, a trailhead pad, ornamental fence and other amenities. Staff stated the phase covered by this bid will be approximately 50% funded by a grant (referenced in the meeting as "onslaught/Ozlad grant") with the remainder from the city parks fund; staff estimated the project's full eventual cost at roughly $1.125 million when later phases and additional amenities are included.

Staff also brought a separate construction-administration agreement with Farnsworth Group to support project management and grant paperwork; the agreement was described as "not to exceed $28,500" and the council approved that contract as well.

The project is expected to start in June 2025 with an anticipated completion around November 2025; staff said some elements (shelter and ornamental fence) will be purchased and installed separately by city staff and volunteers.