Farmingdale updates water projects as county funding arrives and federal commitment is withdrawn
Summary
The Board received updates on AOP/GAC installation at Wells 1–3, additional testing costs (~$16,000 per well), a $1 million county grant (John Ferretti) with $500,000 received, and a later reported withdrawal of a $1.1 million federal commitment; state WIIA funding is capped at $4.6 million.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Philip Ross (Philip Ross Industries) reported that sampling and testing at Wells 1–3 for AOP/GAC installation continues and that the wells are fully operational. A new steel building covering the GAC tanks is complete; staff said additional testing for newly monitored contaminants will cost about $16,000 per well.
Deputy Clerk Daniel Ruckdeschel and meeting minutes note a $1 million grant committed through Nassau County Legislator John Ferretti to offset treatment costs, with $500,000 received. The minutes also record a reported $1.1 million federal commitment in the 2025/2026 federal budget (attributed to Congressman Thomas Suozzi) that staff later said was withdrawn amid a continuing resolution and cuts to discretionary spending. The Village was told WIIA state funding is capped at $4.6 million; D&B is evaluating the ground tank and AT&T/CMS are involved in antenna analyses. Lead and copper letters were mailed to residents with galvanized services.