Committee recommends $6.95M award to BF Anderson for 2025 major storm-sewer repair
Summary
Staff recommended awarding the 2025 major storm sewer repair contract (MS2014) to BF Anderson Builders LLC for $6,950,034.40; staff noted previous phases have reduced floodplain risks for dozens of homes and that portions of construction will be cost-shared with Johnson County.
Get email alerts on the Contract Award topic
No spam. Unsubscribe anytime.
A presenter (speaker 5) described the 2025 phase of a multi-phase storm sewer repair program that will restore approximately 1,800 linear feet of concrete line channel and expand an under-95th-Street reinforced concrete box. Bids opened June 30 and BF Anderson Builders LLC was identified as the apparent lowest and best responsible bidder with a recommended contract amount of $6,950,034.40.
Staff noted the multi-phase program (phases 1–4) is expected to remove 72 homes from the floodplain across all phases and that portions of construction will be cost-shared with Johnson County stormwater. "Staff recommends approving the bid tabulation for the 2025 major storm sewer repair project to BF Anderson Builders LLC in the amount of $6,950,034.40," the presenter said. The committee moved and recommended award to the city council unanimously.