Farmingdale hears $1M county grant and $1.1M federal commitment for water treatment; testing and Plant 2 work ongoing

Board of Trustees, Incorporated Village of Farmingdale · February 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board received updates that a $1 million county grant (half already received) and a reported $1.1 million federal commitment will offset new AOP/GAC water-treatment work at Wells 1–3; additional contaminant testing may cost about $16,000 per well.

Water‑department staff reported ongoing sampling and testing tied to the AOP/GAC installations at Wells 1–3 and said the wells are now fully operational. The board heard that additional testing for newly monitored contaminants may cost approximately $16,000 per well. Philip Ross is cited in the record as overseeing sampling and testing activity.

The board was told a $1 million grant was committed through County Legislator John Ferretti to offset water‑treatment costs and that $500,000 of that amount has been received. The transcript records that Congressman Thomas Suozzi informed the village of a $1.1 million commitment in the 2025/2026 federal budget; the note specifies it is not a reimbursement grant. Plant 2 construction and a PRI master schedule were reported as ongoing with an expected completion target of May 1, 2025.