Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Road Projects topic

No spam. Unsubscribe anytime.

Council reviews Main Street resurfacing and New Street speed-hump evaluation

Mayor and Council of the Borough of Stanhope · May 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Borough Engineer Eric Keller updated the council on Main Street milling and resurfacing and outlined a New Street Local Aid proposal that includes review of existing speed humps; the crosswalk material was approved by NJDOT and the engineer will schedule Portofino to complete work.

At the work session the borough engineer updated the council on two Local Aid resurfacing projects and traffic-calming options.

Keller said Portofino will complete crosswalk treatments on Main Street using an NJDOT-approved cementitious material to replace thermoplastic that had been pulled up. He also outlined the New Street Local Aid proposal and said staff will evaluate whether the current two speed humps need rotation or whether additional humps are required; he told council the speed-hump work cannot be done through the co-op because it is not a contracted item but that he believes the cost will fall below the bid threshold.

Councilman Smith asked whether a three-way stop could be placed at New Street and Plane Street if additional speed humps were not recommended; Keller agreed to investigate and also to review Plainview Street at the request of Councilman Wachterhauser. Keller said he will schedule the Main Street crosswalk work once the contractor and material substitution are finalized.