Whitman County Board of Adjustment approves variance and conditional use permit; no public opposition recorded
Summary
The Board unanimously approved VAR 26‑001 (Two‑GM, LLC setback reduction) and CU 26‑001 (Inland Power & Light Jerita Substation expansion) on March 12, 2026. Notices were published and mailed; the transcript records no public comments for either item.
Get email alerts on the Meeting Roundup topic
No spam. Unsubscribe anytime.
At its March 12, 2026 public hearing, the Whitman County Board of Adjustment approved two land‑use decisions: Variance VAR 26‑001 for Two‑GM, LLC to reduce a westerly side setback to 10 feet at 5951 Pullman Airport Road, and Conditional Use Permit CU 26‑001 for Inland Power & Light to expand the Jerita Substation in Lacrosse with a 7,500 sq ft gravel pad. Both votes were unanimous.
Board procedures followed standard practice: staff read Findings of Fact and Conclusions of Law; members polled the four statutory variance findings for VAR 26‑001 and recorded the CU 26‑001 conditions (required permits, permit continuity with ownership, and full‑cutoff outdoor lighting). Notices for both matters were published in the Whitman County Gazette and mailed to adjacent property owners within 300 feet; the transcript notes no written comments were received for either application. The Board closed hearings and adjourned the meeting.