Project manager updates council on facilities master plan: RFQs, cost updates and CEQA planning

Town of Ross Town Council · April 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project manager David Kelly reported updated cost estimates (including escalation to 2030), an Election Code fiscal-impact study tied to the FORF initiative, RFQs for affordable housing and architectural/engineering services (SOQs received), and plans to stage environmental review with consultants after the Citizens Advisory Committee recommendation.

David Kelly, the town's project manager for the facilities master plan, provided the council's third implementation update. He said cost estimates for Concept B and a paramedic facility were updated in December to reflect escalation through 2030, and staff published a fiscal-impact (Election Code) study that informed the council and voters about implementation costs tied to the FORF initiative. Kelly reported RFQs: the affordable-housing RFQ and an architectural/engineering RFQ were released; one SOQ had been submitted for the housing RFQ and multiple SOQs were expected for engineering services by the listed due date.

Kelly explained that the earlier Gantt schedule remains a flexible tool, that environmental review (CEQA) work has been delayed to allow the Citizens Advisory Committee to make recommendations, and that staff will hire subconsultants to inform the CEQA process once scope and sites are clearer. He said the next steps are SOQ review, interviews and bringing recommended professional service agreements back to council for approval.