Ringgold County proceeds with multiple culvert replacements and right-of-way clearing
Summary
County Engineer Jared Johnson briefed the board on three work orders: W.O. 1448 (completed) on J55, W.O. 1470 (in progress) on 325th Avenue, and W.O. 1481 (in progress) for right-of-way clearing near 210th Street and 220th Avenue.
Get email alerts on the Culvert Replacements topic
No spam. Unsubscribe anytime.
County Engineer Jared Johnson provided specifics on active and completed work orders during the July 27 Board of Supervisors meeting.
Johnson reported W.O. 1448 is complete: crews replaced a deteriorated 48‑inch CMP culvert with a 48‑inch ADS broken‑back culvert along J55 between 110th and 120th Avenues. He said W.O. 1470 is in progress and will replace a deteriorated and washed‑out 84‑inch CMP culvert with a 10‑foot tanker‑car culvert and will armor the inlet and outlet with revetment on 325th Avenue between 170th and 190th Streets. W.O. 1481 is underway to clear brush and trees along approximately 0.5 miles of right‑of‑way near 210th Street and 220th Avenue.
Supervisors did not take separate votes on individual work orders during the meeting; the items were reported as part of the engineer’s routine update.