MPWA approves $5,000 land purchase for new water tank; maintenance team reports progress on street and meter work
Summary
The Medford Public Works Authority bought roughly 1 acre from Roger Shire for $5,000 to site a water tank and reported completion of 13 street repairs, meter installs and ditch maintenance at the May 15 meeting.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The Medford Public Works Authority approved purchase of about 1 acre in the E1/2 SE1/4 of 6‑26‑5 from Roger Shire for $5,000 to reserve a site for a new water tank to meet customer demand. Steve Zeman moved to purchase the land and Shari England seconded; the motion carried with recorded votes in favor.
MPWA maintenance staff reported several operational items: 13 streets completed under a paving project, repaired concrete near a grocery‑store employee parking area, installed Dig Rite’s water meter, hung Veterans Memorial flags, and ongoing ditch and tin‑horn cleaning to aid drainage. MPWA approved its April minutes, financial report ($41,173.14) and claims ($40,722.65) and adjourned at 5:30 p.m.