Sevier County reports ARPA water projects nearly complete; Millican Grove awaiting state approval
Summary
County staff reported Oma Lee and Deer Meadows ARPA water projects are complete (6 and 12 customers respectively); Pittman Center is roughly 80% complete and Millican Grove awaits final state approval.
Get email alerts on the Arpa Projects Status topic
No spam. Unsubscribe anytime.
Director Brent Shults told the Water Committee that several ARPA-funded water projects are at or near completion: Oma Lee is 100% complete with six customers tied on, and Deer Meadows is 100% complete with 12 customers tied on. The Pittman Center project is approximately 80% complete with four customers tied on, and staff expect additional connections as that project finishes.
Robert Campbell of Robert Campbell & Associates said the Millican Grove project is pending final approval from the State. No construction timeline or start date for Millican Grove was provided at the meeting; staff indicated the county will await state sign-off before proceeding.