Early‑childhood project change orders: $3,431.44 add, $15,330 deduct; project remains near schedule
Summary
The board heard facility updates on change order #7 (add tack-board trim, $3,431.44) and change order #8 (deduct $15,330 for use of an alternative safe cable). Staff reported the project is under 3.36% in total change orders and is moving ahead of schedule.
Get email alerts on the Construction Projects topic
No spam. Unsubscribe anytime.
Facilities staff updated the board on two change orders for the early‑childhood project at the Special Education Center. Change Order 7 added trim on preschool tack boards to prevent fraying at a cost of $3,431.44. Change Order 8 was a negative (deduct) change order of $15,330 due to an incorrect but code‑compliant electrical cable that cost less than the originally specified cable.
Facilities staff said the net effect of recent change orders is a total below $120,000 (approximately 3.36% of the total project). The project team reported the preschool substantial completion target is around June 20 and the district office around July 14, both described as soft dates dependent on final work and inspections.