Board awards $39,183 procurement for Corporation Yard interior doors; staff to install

Lake Arrowhead Community Services District Board of Directors · December 10, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board approved a $39,183 procurement contract with RBI to supply 17 interior commercial doors for the Corporation Yard project; District staff will perform installation, saving the District an estimated $60,000 compared with an outside installation bid.

Engineering Manager Scott Schroder explained the Corporation Yard bid omitted interior doors and the District solicited quotes for 17 commercial doors and hardware. Two estimates arrived: one included doors and installation at over $100,000; the other (RBI) would supply doors only.

District staff elected to install the doors in-house to save money. The Board approved a $39,183 procurement contract with RBI for the doors; Schroder estimated total project costs, including engineering and inspections, of about $47,804. Director Morris noted an estimated $60,000 savings for ratepayers and President Wurm thanked staff for "saving the rate payers money."

The Board authorized the General Manager to execute the contract. Staff will schedule delivery and coordinate in-house installation to meet project timelines.