Summary

HPCA leaders and residents asked the Heritage Pines CDD on April 15 to consider a liaison and potential financing for a proposed multi-purpose building; the Board said it needs engineering drawings and cost opinions before deciding whether CDD funds or financing can be used.

HPCA President Gary Farley asked the Heritage Pines Community Development District board for a joint workshop and for the CDD to name a Board liaison to the HPCA Fitness Committee and the proposed multi-purpose building project.

District Manager Chuck Adams said the CDD needs engineering drawings to evaluate participation. "With drawings of at least 60% complete, the Engineer’s Cost Opinions can be compiled," Adams said, and added that those cost opinions are necessary to determine whether the CDD could fund specific infrastructure without creating a tax-exempt "destination" issue. Adams explained that "horizontal" infrastructure — "sidewalks, curbs, gutters, drainage system, water and sewer, etc., that would be conveyed to another entity" — generally does not raise the same tax-exempt financing concerns as "vertical" infrastructure such as buildings.

Speakers discussed financing paths and next steps. Farley said the HPCA plans to spend an estimated $15,000 to have the District Engineer prepare drawings for the site and underground work for submittal to the Southwest Florida Water Management District (SWFWMD). Adams outlined financing options the CDD could use if it chose to participate, including a five-year private placement note and a separate Special Revenue Fund to budget annual principal and interest. He noted that sealed bidding procedures would apply above a cost threshold of about $470,000.

Several residents raised governance and scope questions. Resident Mark Kleeman said consulting the right mix of design and construction professionals matters for project management. Adams and board members emphasized that the CDD can designate a single liaison (Mr. Putman was selected by consensus) but that a liaison does not make decisions for the Board and only one supervisor may attend HPCA meetings without triggering Sunshine Law limits.

The Board did not make a funding commitment. Adams said the CDD might fund horizontal infrastructure up to the edge of the building or reimburse HPCA for eligible work, but stressed that the CDD must receive equal value in exchange and that any transfer of assets would require appropriate documentation such as a Bill of Sale and easements. The HPCA will return with engineering drawings and cost opinions for the CDD to consider at a future meeting.