S.D. DOT reports $1.79M in March construction change orders; several projects see large adjustments
Summary
The Commission reviewed construction change orders completed in March that increased contract amounts by $1,789,700.59 (a 1.77% change over the past 12 months), with notable adjustments on Aberdeen-region rout-and-seal and Brookings-area bridge overlay projects.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Craig Smith, Division Director of Operations, presented the Department's March construction change orders, reporting that CCOs completed in March resulted in a $1,789,700.59 increase to original contract amounts; over the past 12 months, the total change to original contracts increased by 1.77%.
Smith highlighted specific projects: IM 0295(46)139 (I-29 S from SD 30 to SD 28) showed a net change to date of $1,055,002.67 after a $287,314.36 CCO to adjust quantities and add work to prevent concrete buckling; NH-P 0011(316) (rout & seal in the Aberdeen area) increased by $165,580.24 (60.5%) after additional crack sealing was required. Project P 0324(06)357 (SD 324 over Medary Creek) had a $231,781.30 CCO to remove unsound concrete discovered during construction. The Commission received the informational report; differences reflect as-built quantities and added work.