City engineer outlines phased plan and budget work to right‑size Cabrillo Mole terminal project
Summary
City Engineer Bob Greenlaw updated council on Phase 2 of the Cabrillo Mole revitalization: after contractor pricing exceeded initial estimates, staff pursued value engineering, reduced building massing and are targeting a $20M project with $17M available now; procurement steps include wharf‑infill bids and a progressive design‑build RFP aimed at a 2026 award and an 18–24 month construction schedule.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Bob Greenlaw, Avalon’s city engineer, delivered an extensive update on the Cabrillo Mole Phase 2 terminal project, tracing the effort from a 2022 design‑intent stage through contractor outreach and value engineering. He said initial engineer estimates were about $15.7 million but that some contractor design‑build teams returned pricing in the $31–42 million range, prompting a right‑sizing exercise that eliminated the second story and simplified the concourse to reduce costs.
Greenlaw said available funding at this point is approximately $17,000,000 and staff are targeting a $20,000,000 project goal with a priority of not putting the city into debt. He described near‑term procurement: bids received for wharf infill; equipment and temporary facilities procurement targeted for November; a progressive design‑build RFP planned in October with interviews in December and a contract award expected in 2026. The plan calls for temporary ticketing and restroom facilities, modified taxi and golf‑cart flow during an 18–24 month construction window.