Avalon approves $270,000 redesign and change order for 206 East Whitley retaining wall to support housing site
Summary
Council authorized a $270,000 contract increase to redesign a retaining wall at the 206 East Whitley housing site after manufacturer requirements and subsurface conditions required switching to a gravity wall; staff said the revision will enable future housing density and improve safety and parking.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Avalon City Council authorized a roughly $270,000 change order to the construction contract for the 206 East Whitley retaining wall after engineering and manufacturer input required a redesign.
Public works explained that the original plan used a mechanically stabilized earth (MSE) wall but the MSE block manufacturer required a deeper foundation and did not accept the adjacent pink retaining wall as a starting tie‑in. "We said, forget that design. We need to go back to a gravity retaining wall ..." staff said, describing a new design with a two‑foot footing, reinforced concrete‑filled block and frequent rebar tie‑backs to support anticipated future surcharge from additional units.
Council authorized the city manager to execute the contract amendment with Jordan Construction Inc., increasing the contract sum by $270,000 for a total not to exceed $987,255, and approved a budget amendment to allocate additional CIP funds. Staff said construction restart was scheduled in November with an objective to finish by year‑end.
Next steps: contractor to resume work per revised design; staff to report progress to council as needed.