Summary

The council approved staff’s recommended 'Option 2' design for a consolidated operations complex and authorized the finance director to pursue full faith and credit funding up to $45,000,000 to preserve the project schedule; staff described cost-share scenarios and potential utility-fee options to cover debt service.

The West Linn City Council on Nov. 18 approved the staff-recommended design direction ("Option 2") for a new operations complex and authorized staff to pursue a full faith and credit financing package of $45 million to keep the project on schedule.

Staff and the project team presented a value-engineered approach that stacks the administration building over fleet and maintenance facilities to reduce earthwork and retaining-wall costs while retaining most operational programming. Project manager Morgan Lovell and the design/construction team described trade-offs that reduced covered parking and a couple of maintenance bays but removed the need for a 30-foot retaining wall and cut roughly $10 million compared with a previously considered option.

Finance staff presented funding scenarios for the $45 million budget: combined annual debt service of approximately $3.2 million distributed across streets, utilities, parks and general funds under a 30% streets cost-share scenario (streets fund annual debt service ~ $962,000). Staff said sale proceeds of surplus property and the current budget baseline improve the scenario; they also modeled a higher-cost $55 million option and hypothetical small utility-fee supplements (e.g., $7/month per household) as potential gap-closers. Council emphasized communications plans and scheduled more detailed financing work in December.

A motion to move forward with Option 2 and to authorize the finance director to secure full faith and credit funding in the amount of $45,000,000 (staff will return with formal adoption of debt resolution) passed unanimously. Council stressed that the Nov. 18 action authorizes design and financing authorization steps to preserve a dry-weather construction start window; the formal debt-authorizing resolution will be presented at a future meeting for final approval.