Pekin CSD 303 schedules demolition, asbestos abatement, and classroom rebuilds in A building
Summary
The committee outlined demolition and asbestos abatement in several A building classrooms this summer and a phased renovation strategy to finish some rooms over the summer and renovate others during the school year; specific rooms named include those assigned to Eric Myers, Alyson Smith, Beau Sheppard, and Eric McCann.
Get email alerts on the Classroom Renovation topic
No spam. Unsubscribe anytime.
Committee members reviewed a multi-room renovation plan for the A building. Minutes state that rooms assigned to Eric Myers and Alyson Smith are "almost complete," while demolition and asbestos abatement are planned for rooms associated with Eric McCann, Beau Sheppard, Health Occupation, Alyson Smith, and Eric Myers.
The committee recorded that construction on Beau Sheppard's and Eric Myers' rooms will be completed over the summer, while other rooms will be renovated during the school year when classes are not held in them. Staff also noted lighting work is complete in A200 and that Brock Horowitz’s room and a new ED/BD room will be worked on once students are out.
No formal approvals or budget vote were recorded in the minutes; the timeline for finishing the larger A building remodel was described as targeting completion by the 2027–2028 school year with substantial in-house work by district staff.