Consultant outlines Bellflower Unified facilities master plan; restrooms, safety and HVAC top priorities

Bellflower Unified School District Board of Education · February 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Consultant Mr. Jackson presented a five‑phase facilities master plan for Bellflower Unified, explaining site assessments, five‑year enrollment projections, and a public input process that surfaced restrooms, safety/security and air conditioning as recurring priorities. He said the plan will include project cost estimates and sequencing to guide future capital decisions.

Consultant Mr. Jackson told the Bellflower Unified School District board that his team is building a centralized database from facility records, principal interviews and on‑site engineering assessments to generate scopes of work and costed project packages.

"We're also sending 3 teams of technical experts onto each of your sites, to look at roofs, building systems, and, outdoor and indoor site conditions," Mr. Jackson said, describing separate engineering teams for building envelope, mechanical/electrical/plumbing/low‑voltage systems, and architects for interiors and site conditions. He said the plan will pair those findings with five‑year enrollment projections from a demographer to prioritize projects districtwide.

Mr. Jackson summarized community outreach so far: focus groups, PTA input, three student listening sessions and an online survey with roughly 228 respondents. He said common themes emerged across stakeholder groups: restroom upgrades, safety and security improvements, better indoor air conditioning, and targeted investments tied to program needs such as science labs and athletic facilities.

Board members asked about the survey sample and how project costs will appear in the deliverable. Board member Stewart asked whether the "228 total" included parents and students; Mr. Jackson confirmed it did. Mr. Jackson said the final plan will show "fully encumbered costs" — not just construction but soft costs and escalation — and that the team works with cost estimators to produce realistic price tags and sequencing recommendations.

The consultant also said the master plan will produce consistent site plans and concept graphics that the district can use for planning, state grant eligibility and, if the board chooses, to inform any future bond measure. Mr. Jackson encouraged board members to communicate any site‑specific priorities to staff early so they can be included before cost estimating begins.

What happens next: Mr. Jackson said site assessments are imminent (teams starting in the weeks ahead), the consultant will share drafts and be available for follow‑up board presentations, and the district will post materials and a shorter public survey on the facilities website to collect broader input.