District and CMAR outline construction-manager-at-risk schedule and contingencies for Hornet Stadium

FLOUR BLUFF ISD Board of Trustees · July 31, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Flour Bluff ISD heard a detailed walkthrough of the CMAR procurement and schedule that anticipates an August 17 start, phased estimates and a target substantial completion next summer; contractors emphasized early subcontractor involvement and contingency allowances.

District and contractor representatives explained the construction‑manager‑at‑risk (CMAR) approach for the Hornet Stadium project, emphasizing early contractor involvement, iterative cost estimates and a menu of alternates to manage budget pressure. The CMAR team said early releases (stadium lighting and demolition of the visitor press box) have already begun and that the full site mobilization is planned for August 17.

Chris Brzoski, who introduced himself during the presentation, described how the contract and bid package include owner and contractor contingencies and a grandstand pier allowance to address unknown foundation conditions. He said the schedule allows subcontractors to see a six‑week look‑ahead and that the district will receive monthly progress updates. "We've got the schedule on our bid package, so that way all the subcontractors... know when it's supposed to start, when it's supposed to be finished," he said. Trustees praised the speed of work and the collaborative process during Q&A.