PV installation on track for August completion, consultants say
Summary
Perkins Eastman and project representatives reported that PV material deliveries have begun, inverter assemblies are underway and racking sleds are in place; the PV system is on schedule for completion by the end of August.
Get email alerts on the Pv System topic
No spam. Unsubscribe anytime.
Project consultants reported that the photovoltaic (PV) system installation at Cromwell Middle School is progressing and remains on schedule for completion by the end of August.
Joe Culotta said submittals are being processed, the system layout is underway, and material deliveries to the site began on Monday; several inverter assemblies have already been completed. Chris Archer added that materials are being stored in a conex box and that racking sleds have been installed. The team described the PV installation as currently "ahead of schedule," and estimated completion by the end of August.
The committee did not take a formal vote on the PV schedule; consultants said they will continue to provide weekly updates and final closeout documentation as the work completes.