Manager reports lift‑station failure, repair quotes and coordination with MDOT on M‑59 paving
Summary
Manager Mike Luce reported the lift station serving the water treatment plant was not pumping backwash and presented two repair quotes; staff may accept a $26,023 mechanical repair quote and a $23,475 worst‑case locating/repair quote. Luce also reported coordination with MDOT on the M‑59 paving project and preliminary gateway sign quotes.
Get email alerts on the Infrastructure Repairs topic
No spam. Unsubscribe anytime.
Manager Mike Luce told trustees that during backwashing the lift station outside the water treatment plant is not pumping backwash to the sanitary sewer. Staff pulled and tested the pumps and found they appeared to be operable; additional investigation is required to determine why the pumps are not moving the backwash. Luce said two quotes were received: CSM Mechanical submitted the timeliest and most economical quote for mechanical repairs (quoted at $26,023) and a second, worst‑case locating and repair quote to find a blockage was $23,475.
Director Scott Hable described pipeline constraints that make camera inspection difficult (1500‑foot run lacking manholes) and noted staff are weighing options including boring a line to a different manhole north of the plant. Luce said staff will return with a recommendation and that the repair work and locating effort would be brought back to the Board at a future meeting.
Luce also said he has been coordinating with MDOT, the Livingston County Road Commission and developers on design changes tied to MDOT’s M‑59 paving timeline (expected 2027) and briefly discussed possible gateway signage on M‑59, including options and vendor quotes.