County schedules repairs after first‑floor leak; HVAC control quotes taken under advisement
Summary
Facility Manager reported a first‑floor leak repaired by Leach & Russell with wall repairs scheduled Nov. 10–12; four HVAC control quotes from three companies were presented, one delayed by an IT error, and the board postponed the procurement decision to the next meeting.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Facility Manager (listed in the transcript as Meagan/Megan Westfall) told the commissioners a first‑floor leak was quickly fixed by Leach & Russell but caused wall damage; repair work is scheduled for Nov. 10–12. She also presented four quotes for HVAC controls from three companies; one Leach & Russell quote arrived late due to an IT error. The board took the HVAC quotes under advisement and will decide at a future meeting.
The meeting record does not include the dollar amounts of the quotes or the names of the other vendors in full beyond those referenced; commissioners asked staff to return with a recommendation at the next meeting.