Developer outlines Suntex Marina plan, warns Army Corps review could add nine months

Fort Myers City Council (workshop) · December 9, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Suntex representatives showed a conceptual upland-and-marina plan that would add roughly 40,000–50,000 sq ft of built space, but presenters said federal permitting—especially consultation over an endangered "sawtooth" species—could extend review by roughly nine months.

Suntex Marinas project director Eric Metz presented a conceptual site plan and timeline for the Suntex Marina redevelopment, describing an upland programed area and expanded marina infrastructure. Metz said the upland component would total "somewhere between 40 to 50,000 square feet of built space," and that the design attempts to balance public promenade access with the grade separation required by FEMA flood-elevation rules.

Metz told council that the finished floor elevation for the upland buildings is about Elevation 14 while the existing road grade is near Elevation 4, creating a roughly 10-foot grade difference that complicates pedestrian access and site programming. He said the project team is coordinating with the Florida Department of Environmental Protection for drainage permits and expects the Army Corps of Engineers review to be the biggest scheduling obstacle: "[the Army Corps] is initiating a consultation process now with other agencies... that's probably about a 9 month endeavor, minimum, from today, realistically." The firm listed habitat consultation over the locally noted "sawtooth" species as the key driver of the Corps' extended timeline.

Council members pressed whether the city review process is running in parallel with state and federal reviews and whether public access would be limited. Metz said the marina and promenade are intended to be open to the public; security gates would protect docking areas but the promenade and sidewalks would remain publicly accessible. On the pier, Metz said the project expects to include a larger face dock and wave attenuator but that final geometry could change based on permitting and the Corps' alternatives analysis.

What happens next: staff and the developer will continue design and permitting outreach; Metz said an upland site plan submission to the city could arrive in January or February, subject to modification after federal review. Council questions focused on timing, drainage coordination and maintaining pedestrian access amid FEMA-elevation constraints.