Commissioners approve change order raising Rattlesnake WWTP GMP to $18.36 million
Summary
The Fayette County Board approved Contract Change Order #9 for the Rattlesnake Wastewater Treatment Plant that adjusts owner contingency and raises the guaranteed maximum price to $18,362,483; the motion carried despite one commissioner recorded as absent at roll call.
Get email alerts on the Rattlesnake Wastewater topic
No spam. Unsubscribe anytime.
The Fayette County Board of Commissioners on April 27 approved Contract Change Order #9 for the Rattlesnake Wastewater Treatment Plant project, adjusting contingencies and increasing the project’s guaranteed maximum price to $18,362,483.
According to the resolution, the change order deducts $91,450 from the embedded owner contingency and adds $72,945 with depletion of owner contingency for specific work requested by Peterson Construction. The motion to accept the change order was recorded as moved by Donald L. Fleak and seconded by Tony Anderson; roll call recorded James D. Garland — aye; Tony Anderson — aye; Donald L. Fleak — absent. The motion carried. The change order and full supporting documentation are on file with county records.