Terminal project on hold as board reviews options after rotting beam findings; repair estimate $250,000
Summary
Operations staff reported the terminal project is on hold pending decisions about rotting terminal beams; preliminary cost estimates to repair or replace the beams are $250,000 and options are under review.
Get email alerts on the Terminal Repairs topic
No spam. Unsubscribe anytime.
The Lancaster Airport Authority heard that the terminal renovation project is paused while staff review options to address rotting terminal beams. Director of Operations & Development Austin Beiler said estimated costs to replace or repair the beams are $250,000 to date and the board is reviewing alternatives.
Beiler said the hangar work is restarting and airlines currently use multiple office spaces; he answered a question from Secretary Casey Clugston about airline space needs. The minutes also note the gravesite project remains under judicial review. The board did not authorize a capital appropriation at this meeting; staff said they are reviewing options and will return with recommendations.