Staff proposes downtown sidewalk program; board asks staff to study CID option

Smithville Board of Aldermen (Work Session) · July 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff proposed a downtown sidewalk repair program based on the city’s 50/50 residential cost‑share model and recommended exploring a community improvement district (CID) to fund broader downtown improvements; staff estimated roughly $120,000 to address 30+ problem locations.

Staff presented a proposed downtown sidewalk replacement program patterned on the residential 50/50 cost‑share approach: the city would fully fund sidewalk damage caused by stormwater infrastructure and ADA ramps, and share 50% of other eligible repairs with property owners in a selected downtown boundary.

"We have identified more than 30 issues in the downtown area, and an estimated cost will be $120,000," the presenter (speaker 9) said, outlining cost, phasing and inspection rules. Under the 50/50 scenario staff estimated the city’s portion would be about $60,000 and owners’ share roughly $30,000 in the first phase, with the remainder paid as property owners join the program.

Staff recommended two options: phase the work across years within the existing sidewalk program or explore forming a CID with the Main Street district to fund larger downtown improvements. The presenter said a CID could fund sidewalks and other public‑realm work but would require property‑owner votes and further research.

The board directed staff to study the CID option and return with a proposal for consideration as part of the 2027 budget process.