Montgomery Selectboard reviews $96,566 estimate for streetscape permitting and right-of-way work

Town of Montgomery Selectboard & Water Commission · December 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Selectboard reviewed a staff-provided cost estimate of $96,566 for Streetscape Tasks 4 (permitting) and 6 (right-of-way)—$41,184 for permitting and $55,382 for ROW—and discussed legal-fee estimates and whether ROW clearing can occur before permitting with VTrans.

Selectboard members reviewed a staff spreadsheet showing a combined estimate of $96,566 for the Streetscape project's permitting and right-of-way tasks. The breakdown given was $41,184 for permitting and $55,382 for right-of-way acquisition or work.

Board members asked staff to obtain a legal-fee estimate tied to a parcel list and to confirm with VTrans whether right-of-way clearing can proceed prior to completing permitting; no action was taken at this meeting beyond requesting follow-up information.