Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
TUHA outlines $4.5M waterline replacement and $1.8M sewer conveyance project; board notes funding sources
Summary
Upper Hanover supervisors heard TUHA updates on a planned $4.5 million capital water line replacement (with a $1 million grant reducing Authority share to $3.5 million) and a $1.8 million sewer conveyance project funded by $1.2 million in user fees and $600,000 in reserves; the TUHA adopted a $4.1 million 2025 operating budget.
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
Ben Fiorito reported on projects of the Township Utilities and Housing Authority (TUHA), saying the authority plans a capital water line replacement stretching roughly 2 miles from Route 29 near Hereford Elementary toward East Greenville. The existing line dates to 1896; the project’s gross cost is estimated at $4.5 million, and a $1 million grant was secured, leaving a $3.5 million authority share to be funded from cash reserves. Bid advertisement is hoped for in June with a projected 6–8 month construction window.
Fiorito also reported planned implementation of the Act 537 sewer conveyance improvements, with an estimated cost of $1.8 million to be paid by $1.2 million in user fees and $600,000 from cash reserves, and anticipated late‑summer construction with completion estimated in early 2026. The TUHA adopted a 2025 operating budget totaling $4.1 million.
