Board ratifies two change orders for Foothill High tennis courts totaling $45,805.93
Summary
The Board approved two change orders for Foothill High School tennis courts—Change Order No. 1 for $36,478.31 and Change Order No. 2 for $9,327.62—citing subgrade changes to improve court longevity; both were carried 4-0.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Associate Superintendent David Flores told the Board that unforeseen changes to the subgrade at Foothill High School required two change orders to ensure the longevity of the new tennis courts. The Board ratified Change Order No. 1 for $36,478.31 and Change Order No. 2 for $9,327.62, recorded in the minutes as Resolutions 25-210 and 25-211.
Flores framed the requests as necessary to maintain project integrity, and trustees approved both change orders by the recorded votes shown in the adopted minutes (each carried 4-0). The district identified Sunrise Excavating as the contractor in the minutes; the approvals authorize net increases to that contract.