Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Stormwater topic
No spam. Unsubscribe anytime.
Engineer and staff outline stormwater, grading and buffer conditions for proposed church
Summary
Staff and the applicant's engineer said stormwater will be handled with bioswales and a detention pond; the Phase 1 pond is oversized to be adapted for Phase 2 and any temporary buffer disturbance must be replanted to buffer standards.
Get email alerts on the Stormwater topic
No spam. Unsubscribe anytime.
Staff described required stormwater controls and buffer planting standards for the project, and the applicant’s engineer explained how pond and bioswale work will be staged across the two phases.
During the presentation, staff said the applicant “would construct an above ground stormwater management facility and infiltration areas in the form of bioswales to comply with the city's stormwater management regulations.” Commissioners asked how grading in buffers would be treated; staff said temporary grading would be allowed for construction but disturbed areas must be replanted to buffer standards at land‑disturbance permitting. Engineer John Wise told the commission the Phase 1 pond was designed larger than strictly needed for early construction so it can be modified later to accommodate Phase 2 as parking is added: “It's much larger than it needs to be for phase 1,” he said, explaining that storage is available for future buildout without rebuilding the pond.
Commissioners conditioned approval recommendations on final engineering and required revegetation at the permitting stage; those details will be reviewed if City Council approves the recommendation.
